|
|
|
|
|
INTEGRATED
WATERSHED DEVELOPMENT PROJECT Name
of the scheme :- CENTRALLY
SPONSORED SCHEME (MORD) FOR DEVELOPMENT OF
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
In the Central and
South-Western parts of Haryana, underground water is mostly not fit for
irrigation. Therefore, to meet the irrigation requirements, canal irrigation
is being used. As a result of less withdrawal of the ground water and more
recharge from surface irrigation, the water table in the area over a period
of time has come up on the surface, along with salts. Water logging leads to
salinity problems. This has adversely affected the crop production. To
maintain sustainable production, reclamation of saline and waterlogged soils
is needed. According to rough estimate, about 4.00 lakh hectares area in the
State is affected with this problem, out of which about 40,000 hectare is
under critical condition i.e. water table within 0-1.5 meter.
The saline and
waterlogged area occurred along with the canals due to seepage and mainly
falls under the districts of Rohtak, Jhajjar, Sonepat, ,Bhiwani, Hisar, Jind
, Sirsa, Fatehabad & Mewat,. The
reclamation of such soil may be carried out by drainage i.e. surface
drainage, bio-drainage, vertical drainage & horizontal drainage (Sub
Surface Drainage). The Sub Surface
Drainage work undertaken by the Agri.Department.
A. INDO-DUTCH PROJECT
A project for the reclamation
of water logged and saline lands in Haryana was started with the technical
& financial assistance of Govt. of Netherland in October, 1994 and it was
named as Haryana Operational Pilot Project (HOPP). Under this project, an
area of 2406 hect. was reclaimed in
Gohana (Sonepat) & Kalayat (Kaithal).
In Sub Surface Drainage System, perforated & corrugated PVC pipes
are laid down horizontally with the trencher machine having automatic laser
leveler at a depth 1.5 to 2.00 meter of small dia (Lateral) pipe and at 2.00
to 3.00 meter depth of big size dia (Collector) pipe. The lateral pipe are
wrapped with filter material and collector wrapped with nylon socks and these
pipes are joined to a sump. The dissolved salts of surface and root zone are
leached down in these perforated pipes and collected in a sump from where
this salty water is lifted and drained out in a drain/canal. Technically,
this system has proved very good for reclamation of saline and water logged
soils.
B.UNDER MINISTY OF RURAL DEVELOPMENT
(MORD) (GOI+STATE) SCHEME.
After the
success of the Indo-Dutch Project in Gohana & Kalayat area, Govt. of
India, Ministry of Rural Development were sanctioned four projects with a
cost of Rs.19.06 crore for Sonepat, Jhajjar Bhiwani & Sirsa districts
covering an area of 4600 hectare. Now Department of Agriculture has targeted
to reclaim 4600 hectare in four districts on the sites of Dadri (Bhiwani),
Beri (Jhajjar), Rori (Sirsa) and Dhanana (Sonepat) and has reclaimed 3325
hectare land so far. The
construction/Pipe laying work at Jhajjar & Bhiwani, Sirsa & Sonepat districts have been completed. Three Trenching machines are working
on three different sites at a time.
The work in Bhiwani & Sirsa sites was entrusted to HLRDC. The share of
Govt. of India & State Govt. was in the ratio of 60:30 while 10%
contribution from the farmers was being made. The cost of reclamation with
the laying out of SSD System comes around Rs. 55000 per hectare (approx).
C.
RKVY PROJECT
1)
Fatehabad project
In district
Fatehabad, a project of 600 hectares and a sum of Rs. 285.00 lakh for the reclamation of
Saline & water logged area was approved under RKVY scheme during the year
2008-09. The construction/pipe lying work in 277 hect. has been
completed in village Banmandori the
rest area of the village Gorakhpur
& Kumarian was left due to area
fall under proposed Nuclear Plant
.
2-Jhajjar-II
Project
A project for covering 1000 hectare and a sum of Rs. 475.00 lakh for
reclamation of Saline & Water logged area in village Wazirpur, Baghpur
and Beri of district Jhajjar Phase-II was approved under RKVY scheme during
the year 2009-10. The construction/pipe
laying work in 754 hect. area in village
Wazirpur, Bagpur & Beri has been completed and the rest area was left due to farmers
were not interested as area moderately affected . The remaining work of project is in progress.
3-Palwal
project
In district
Palwal a project covering 700 hectare
and a sum of Rs. 435.00 lakh was approved under RKVY scheme during the year
2010-11. The construction/lying of
pipe work in 240 hect. area completed and the remaining SSD work is in progress.
4-Rohtak
Project
A project
covering 1000 hect. and a sum of Rs. 585.00 lakh has been approved
in May 2011-12 by SLSC under
RKVY for reclamation of Saline & Water logged area in village Mokhra & Rs. 180.00 lakh have approved for the current year. The preliminary work and planning for SSD
work is in progress.
5-Jind
Project
A project
covering 600 hect. and a sum of Rs. 351.00 lakh has been approved
in May 2011-12 by SLSC under RKVY scheme for reclamation of Saline & Water logged area in village
Siwanamal & Gangana & Rs. 190.00 lakh have approved for the current year. The preliminary work and planning for SSD
work is in progress.
The execution
of SSD works is peculiar in nature and could be carried out in fallow fields
i.e. during the months of April to June and for a short period in the months
of October-November. The availability of fresh water and a surface drain are
essential for laying out of this system.
BUDGET
PROVISION FOR THE YEAR 2011-12
Under RKVY
scheme Rs. 630.00 lakh for lying out Sub Surface Drainage (SSD) work and Rs.
165.00 lakh for the purchase of heavy drainage machineries have also been
approved for the year 2011-12. Now the SSD work is being carried out by three
Trenching Machines at a time at three different project sites by the
department independently. The
strengthening of SSD project is required for covering the more area.
A- SSD
Achievements under Indo Dutch (HOPP) Project
(Area in Hectare) (Rs. In lakh)
|
Sr. No. |
Project |
Villages |
Nos. of Blocks |
Area reclaimed |
Amount released |
Nos. of Beneficiaries |
Remarks |
||
|
|
|
|
|
|
GOI |
State |
|
|
|
|
1 |
Gohana (Sonepat) |
Moi, |
23 |
1253 |
Aided by |
872 |
|
||
|
2 |
Kalayat
(Kaithal) |
Kherilamba,
Kalayat, & Kolekhan & Kurar |
21 |
1153 |
Aided by |
725 |
407 ha. (Rs.
45.72lacs) under MMM Scheme Through HLRDC)
|
||
|
|
|
Total |
44 |
2406 |
|
|
1597 |
|
|
B- SSD Achievements under
M.O.R.D. Scheme(GOI +State Govt. Sharing basis)
|
Sr. No. |
Project |
Villages |
Nos. of
Blocks |
Area
reclaimed |
Amount
released |
Nos. of
Beneficiaries |
Remarks |
|
|
|
|
|
|
|
GOI |
State |
|
|
|
1 |
Jhajjar |
Berikhas,Beridopana,
Gochhi, Dhandlan & Bakra |
14 |
805 |
273.25 |
127.50 |
873 |
|
|
2. |
Bhiwani |
Achina,
Loharwala, Jhinjar & Rawaldhi |
16 |
904 |
295.06 |
127.50 |
963 |
Through
HLRDC |
|
3. |
Sirsa |
Surtia,
darba-Kalan & Nathusri chaupta |
12 |
479 |
126.39 |
98.96 |
180 |
Through
HLRDC |
|
4. |
Sonepat |
Dhanana,
Rindana, Jagsi & |
23 |
1137 |
126.39 |
98.96 |
836 |
|
|
|
Total |
|
65 |
3325 |
821.09 |
452.92 |
2852 |
|
C- SSD Achievements
under RKVY Scheme
|
Sr. No. |
Project |
Villages |
Nos. of Blocks |
Area reclaimed |
Amount released |
Nos. of Beneficiaries |
Remarks |
|
|
|
|
|
|
|
GOI |
State |
|
|
|
1 |
Fatehabad |
Banmandori |
8 |
277 |
144 |
- |
130 |
Through
HLRDC |
|
2 |
Jhajjar-II |
Wazirpur,
Baghpur & Beri |
10 |
754 |
300 |
- |
615 |
Civil work
is in progress |
|
3 |
Palwal |
Kanoli, Madkola, Kherijeeta |
18 |
240 |
150 |
- |
172 |
Work in
progress |
|
|
Total:- |
|
34 |
1271 |
594 |
- |
917 |
|
|
|
G.Total:
A+B+C |
|
122 |
2406+3325+ 1271=7002
uto July 2011 |
|
|
5366 |
|
PROJECTS TAKEN UP FROM 2005-06 ONWARDSFOR RECLAMATION OF SALINE AND
WATERLOGGED SOILS IN HARYANA
(Area in Hect) (Rs. In lakh) . August 2011
|
Sr. No. |
Name of Project |
Location |
Amt. |
Year of Start |
Area reclaimed |
Cumulative Progress |
Remarks |
||||||
|
|
|
|
|
|
2005-06 |
2006-07 |
2007-08 |
2008-09 |
2009-10 |
2010-11 |
2011-12 |
|
|
|
1 |
Jhajjar |
Beri, Beri
Khas,Dhandlan, GochhiBakra |
400.75 |
2003-04 |
296 |
132 |
0 |
0 |
0 |
0 |
0 |
428 |
- |
|
2 |
Bhiwani (Ch.Dadri) |
Rawaldhi,Khatiwas, Loharwara,Achina,
|
422.55 |
2004-05 |
210 |
70 |
189 |
278 |
0 |
0 |
0 |
747 |
Through
HLRDC |
|
3 |
Sonepat |
Rindhana,
Dhanana, Dhanana-II,
Jagsi |
225.35 |
2006-07 |
0 |
216 |
0 |
300 |
430 |
0 |
191 |
1137 |
- |
|
4 |
Sirsa (Rori) |
Suritia,
Darbakalan, & Nathusari Choptas |
225.35 |
2006-07 |
0 |
95 |
0 |
175 |
129 |
80 |
0 |
479 |
Through
HLRDC |
|
5 |
Fatehabad (RKVY) |
Banmandori, |
144.00 |
2009-10 |
0 |
0 |
0 |
0 |
80 |
117 |
80 |
277 |
Through
HLRDC |
|
6 |
Jhajjar-II (RKVY) |
Bhagpur,
Wazirpur, Beri Khas |
375.00 |
2009-10 |
0 |
0 |
0 |
0 |
0 |
423 |
331 |
754 |
Work in
Progress |
|
7. |
Palwal (RKVY) |
Mandkola,Sairoli,
Kanoli, Uleta, Khedli Jeta |
335.00 |
2010-11 |
0 |
0 |
0 |
0 |
0 |
0 |
240 |
240 |
Work in
Progress |
|
8 |
Rohtak (RKVY) |
Mokhra Khas |
180.00 |
2011-12 |
|
|
|
|
|
|
|
|
Preliminary
work is in progress |
|
9 |
Jind (RKVY) |
Siwanamal ,
Gangana |
190.00 |
2011-12 |
|
|
|
|
|
|
|
|
-do- |
|
|
Total |
|
2498.00 |
|
506 |
513 |
189 |
753 |
639 |
620 |
842 |
4062 |
|
INTEGRATED
WATERSHED DEVELOPMENT PROJECT (HILLS-II) , HARYANA
![]()

Background
|
A
part of Shivalik which forms foothills of Himalayan ranges also lies in the
districts Panchkula, Ambala and Yamuna Nagar of
It is a multi-sectoral project where specialists drawn from the department
of |
Objectives
The main objective of the
project is to restore the productive potential of the project area by
developing soil-water plant resources of the watershed to rectify the man
made ecological imbalance by conserving the natural resources on arable
and non-arable lands. The emphasis is to conserve soil and moisture in situ
through integrated approach with bottom up planning & top to bottom
treatment. Phase-wise information is given as below:-
|
Period |
Sub Watershed |
Area (ha) |
Village
(No.) |
|
Initial ( 1990-94) |
Sirsa Boli Yamuna |
8964 6406 |
29 25 |
|
Expansion 1994-97 |
Madhkali Begna Somb Pathrala |
4036 17345 15890 11297 |
8 119 60 40 |
|
Extension |
Dangri |
24858 |
82 |
|
1997-99 |
Nakti |
9458 |
44 |
|
|
Sukhrao |
5930 |
3 |
Total
|
|
104184 |
410 |
In Phase-II there is more emphasis on planning and implementation by the stake
holders. Hence forth works would be executed through village development
committee(VDC) and beneficiaries participation.
In the Second Phase one main component added in rural road component which is
being executed by PWD B&R, Haryana. Second Phase was negotiated in
Number of participating States has increased from four to five with the
inclusion of Uttaranchal.
Activities and
Achievements
1. Watershed
protection and Development
Vegetative shrub barriers :-
Vegetative
shrub barriers are created in contour trenches in order to reduce soil erosion
and improve water retention. Generally, this treatment is applied on
seriously degraded areas with the objective of reducing surface run off
increasing moisture infiltration and trapping soil sediments. Shrub barrier
is done through a small crosssection of V-ditch reinforcement with indigenous
shrubs and grasses which will intercept and reduce run-off.
Field
demonstration is conducted to promote improved agronomic practices like
tillage for in-situ moisture conservation, improved crop varieties, seed
treatment, optimum use of fertilizer and pesticides among the farmers. More
innovative crops are to be taken up after Mid Term Review.
Cultivation of fruit trees in marginal lands has potential in the Kandi
areas. High Yielding fruit plants like mango, guava, amla, lemon etc are
planted in cultivated lands. Vegetable crop demonstrations are also held to
promote vegetable cultivation, diversification and to improve economic status
of the people. After Mid Term Review more emphasis is given growing off
season vegetables.
The objective of the component is to reduce the
pressure of unproductive livestock on the ecologically fragile lands. This is
achieved through breed and fodder improvement, providing better health cover.
This induces stall feeding and help in improving milk yield. Primary emphasis
is being given to breed improvement through artificial insemination, import
of cattle semen etc. veterinary health improvement, fodder production and
improved feed technology.
Rural
Infrastructure Development:-
The objective of this component is to improve access to
potential production and marketing areas to facilitate the communication of
the rural population in the project areas and to improve drinking and
irrigation water facilities. Upgradation, repair and provision of better
cross-drainage structures for the existing rural roads is also done to
facilitate marketing of surplus agriculture produce. Some water points are
being developed to augment the existing water supplies in the Project area
and also for irrigation wherever possible.
Drainage line
treatment:-
This
component envisages to minimize soil erosion along the natural water courses
through various drainage treatment works and erosion control programmes
which include various vegetative and structural measures such as
planting of suitable plant species and construction of check dams, silt
detention dams, cement structures, crate wire structures and vegetative spurs
etc.
Efforts
are being made to provide irrigation
as well as drinking water facilities to the villages of the project area by
storing rainwater through construction of water harvesting structures. The
programme includes construction of village ponds, shallow dams of less than
15 meters height, lift irrigation structures or wells and other water
collection facilities such as roof tanks, channels and earthen dams. Emphasis
is given to minimize silting by ensuring that upstream treatment is complete
and effective.
2. Institutional
Strengthening
Training & Capacity building:-
The project envisages to support beneficiary
capacity building in planning and implementation by sensitizing the
beneficiaries to the maintenance of project assets and interventions. This
too is primarily achieved through extension and by strengthening human
resource development through training and field exposure. Regular training of
VDCs are conducted for strengthening and capacity building so that they can
take the responsibilities of managing natural resources on their own in a
sustainable manner. Project staff is trained on principles and practices on
participatory natural resource management as well as integrated watershed
management. For this purpose co-ordinator and facilitators have been
appointed contract basis.
A
number of activities are undertaken in order to create awareness among the
village community about various activities under the project. These not only
sensitize the village community or beneficiaries but also help in community
strengthening and capacity building. Informal and formal meetings are
regularly held by the project staff to inform the village communities about
the project. Women facilitators have been appointed to facilitate women’s
participation in the project and also to make them aware about the benefits
likely to be accrued.
HARYANA OPERATIONAL PILOT PROJECT
![]()
Background
:
|
The twin problems of waterlogging and soil
salinity are threatening the sustainability of agricultural production in
large parts of
To tackle problem of salinity and waterlogging, a pilot project namely
“Haryana Operational Pilot Project” (HOPP) was started in the State in
October, 1994 with the support of Govt. of Netherlands. |
|
The Department of Agriculture was designated
as the Nodal Department for the HOPP with the soil conservation office as
implementing agency.
Aims & Objectives of HOPP
The specific HOPP objectives are:
The transfer of technology (equipment,
knowledge and skills) relating to the reclamation of waterlogged and saline
land in Haryana.
The construction and operation of two
horizontal subsurface drainage schemes (Gohana and Kalayat), each of about
1,000 hect.
The creation of the nucleus of an organization
in Haryana capable of:
-
implementing subsurface drainage systems on about 2500 hec. Per year and
maintaining the resulting drainage network.
- attracting sufficient funds for
the purchase of additional equipment, the actual construction of
drainage systems and for hiring the required staff.
- The participation of farmers in
the planning, construction, operation and maintenance of the
subsurface drainage systems.
- The environmentally sound disposal of the
saline drainage effluent of the pilot areas.
Activities
The major activity under project is laying of
horizontal subsurface drainage system in waterlogged/saline area with the
help of drainage trencher. In the system, perforated corrugated PVC pipes are
laid horizontally at a depth of 1.7m-3.00 meters of the affected land for
leaching of salty water from the plant root zone.
Apart from this, the participation of beneficiaries in the planning, operation and maintenance of the system is also ensured by forming farmer’s Drainage Societies so as to create a sense of ownership amongst them.
|
|